IRIS
Intelligent Roadway Information System
Density Adaptive Metering
The density adaptive ramp metering algorithm has two main objectives:
- Delay the onset of freeway mainline congestion for as long as possible. This is achieved by restricting metering rates when density on the mainline approaches a critical level
- Effectively manage the queue at ramp meters:
- Release rates should be adjusted gradually
- Wait times should not be longer than a configurable limit — typically 4 minutes
- The queue from the ramp meter should not back up onto cross streets
The ramp queue condition and mainline vehicle density are used together to calculate metering rates.
Queueing
A queue is formed at a ramp meter when the input (demand) is greater than the output (passage). At any point in time, the difference between these counts is the queue length (in vehicles). Wait time is estimated by comparing the passage count with demand counts from previous time intervals. The vehicle at the head of the queue started waiting when demand was equal to the current passage count.
Flow Rate
The slope of accumulated vehicle counts through time is the flow rate. Typically, it is expressed in vehicles per hour. For practical metering on two-lane alternate-release meters, flow can range from 240 to 1800 (about 4 to 30 vehicles per minute).
Queue Data
Vehicle detection systems on the entrance ramp provide data for monitoring the queue. Unfortunately, these systems are not 100% accurate, so special care is needed when using the data. From the time when metering begins, total vehicle counts are recorded for greens, passage and demand.
Green Count
The green count is the number of green indications which have been displayed on the ramp meter. Sometimes called the "release count", it is not a count of actual vehicles, but it is useful in determining whether or not a queue is present.
Passage (Output)
The passage detector is placed just downstream of the ramp meter. The count from this detector is used to estimate the output of the queue. Due to its placement, it usually records the most accurate counts for an entrance ramp.
Demand (Input)
A queue detector is placed on the entrance ramp, upstream of the meter. It should be located at the tail of the longest acceptable queue. The count from this detector is used to estimate the input of the queue. Note: Some installations also have "demand" detectors located just upstream of the meter — these are not usefull for demand counts.
If the queue detector is not counting, demand is set to a fixed target value — specific to one ramp meter and period (AM or PM). It is based on historical demand at the ramp.
Demand Undercount Correction
If the queue backs up over the detector, the occupancy will jump to greater than 25%. When this happens, the detector may undercount vehicles. To correct this, the estimated queue demand is increased gradually until the queue length is equal to maximum storage.
The available storage count is maximum storage minus current queue length. High occupancy duration is the number of seconds that occupancy was greater than 25%. Queue overflow ratio is 2 times the high occupancy duration divided by maximum wait time, limited to a range between 0 and 1. The demand undercount adjustment is equal to the available storage multiplied by queue overflow ratio.
Empty Queue Correction
When the queue is empty, the demand and green counts are adjusted to match the passage count. The following conditions indicate that the queue may be empty:
Queue detector occupancy is below 25%, AND
- Demand count is below passage count, OR
- Passage count is below green count
The empty queue duration is the number of seconds that the queue was empty. The queue empty ratio is 2 times the empty queue duration divided by maximum wait time, limited to a range between 0 and 1. The demand overcount adjustment is the queue length times the queue empty ratio.
Limits
The metering rate is limited by the minimum and maximum rates. These are determined by the state of the ramp queue.
Maximum Rate
The maximum rate is normally 125% of the tracking demand, but it is increased to 150% during the flushing phase. This is to prevent the meter from releasing a queue too quickly. The maximum rate will not be lower than the minimum rate.
Minimum Rate
When the passage detector malfunctions, the minimum rate is equal to the tracking demand. Otherwise, it is the highest of the following 4 limits:
- Tracking minimum limit (75% of tracking demand)
- Queue wait limit
- Queue storage limit
- Backup limit
Queue Wait Limit
The purpose of the queue wait limit is to keep wait times below a maximum limit. All past intervals within the target wait time are checked. Rates are calculated from the current passage to the accumulated demand at those intervals, using the remaining target wait time. The queue wait limit is the highest of those.
When the queue detector is malfunctioning, the target value for the current metering period (AM or PM) is used for demand. This makes the queue wait limit behave as if the demand is high at all times. While not optimal, it allows short queues to be held to break up platoons of vehicles.
Queue Storage Limit
The queue storage limit prevents the queue from becoming more than 75% full. The target storage is subtracted from the accumulated demand, then projected to the target wait time, using the tracking demand. The queue storage limit is the rate from the current passage to that projected target storage.
When the queue detector is malfunctioning, the target value for the current metering period (AM or PM) is used for demand. This makes the queue storage limit behave as if the demand is high at all times. While not optimal, it allows short queues to be held to break up platoons of vehicles.
Backup Limit
When the queue detector occupancy is greater than 25%, a backup limit is calculated. First, the backup factor is "minutes queue detector has been occupied (greater than 25%) multiplied by the average occupancy over that time." Then, the backup limit is the tracking demand multiplied by 50% plus the backup factor.
Mainline Segments
A mainline segment is derived from a contiguous series of mainline stations. The distance between each pair of stations is divided into 3 links of equal length. The first and last links are assigned density from the station adjacent to them. The middle link is assigned a density which is an average of the two stations. The segment density is an average of all links in the segment, weighted by length.
Segment Density
Each meter is associated with a mainline segment at each interval. This segment begins at the station just upstream of the meter. The downstream station must be within 3 miles of the upstream station. It is the station which results in the highest segment density.
Rate Calculation
Mainline segment density will cause the metering rate to be adjusted within the rate limits. The metering rate is calculated iteratively, based on the metering rate from the previous 30 seconds. If the segment density is below the desired density, the rate will increase. Likewise, if segment density is higher than desired, the rate will decrease. When the meter is first turned on, the passage rate averaged over the last 90 seconds is used in place of the previous metering rate.
The previous metering rate is first constrained within the bounds of the new minimum and maximum rates. The new rate is calculated using linear interpolation from the previous rate and density. With segment density between zero and desired density, the rate is interpolated between the maximum rate and the previous rate. With segment density between desired and jam density, the rate is interpolated between the previous rate and the minimum rate.
Metering Period
A metering period begins and ends at specific times during the day. Within the metering period, a meter can be in one of 4 phases: not started, metering, flushing or stopped. When transition conditions are met, the meter moves to the next phase. If all meters on a corridor are in the stopped phase, the metering period ends.
Not Started Phase
Ramp meters begin each metering period in this phase. The meter will not cycle when in this phase. There are two conditions which cause the meter to transition to a different phase. If segment density averaged for 2 minutes is higher than desired density, the phase will change to metering. Otherwise, when only 30 minutes remain in the metering period, the phase will change to stopped.
Metering Phase
In this phase, a ramp meter will cycle at the selected metering rate. The following conditions will cause the meter to transition to the flushing phase:
- Segment density averaged for 10 minutes is below low density, OR
- Only 2 minutes remain in the metering period
Flushing Phase
In this phase, a ramp meter will cycle at the maximum metering rate. The following conditions will cause the meter to transition to the stopped phase:
- The queue is estimated to be empty, OR
- The metering period ends
Stopped Phase
In this phase, a ramp meter will not cycle. The following conditions will cause the meter to transition back to the metering phase:
- Segment density averaged for 5 minutes is higher than desired density, AND
- More than 2 minutes remain in the metering period
Definitions
Term | Definition |
---|---|
Critical Density | Density threshold for identifying high probability of mainline flow breakdown (37 vehicles per lane-mile) |
Density | Vehicles per lane-mile |
Desired Density | Density threshold for determining whether metering is necessary (90% of critical density, or 33.3 vehicles per lane-mile) |
Interval Density | Average of station samples during one 60 second interval |
Jam Density | Density of completely jammed mainline (180 vehicles per lane-mile) |
Low Density | Density threshold for determining whether metering should continue (75% of critical density, or 27.75 vehicles per lane-mile) |
Maximum Storage | Maximum number of vehicles which can be stored in a queue |
Station Density | Average of all valid lanes in a station for one sample period |
Tracking Demand | Average ramp queue flow rate for previous 5 minutes |